Smart Cities Mission
GOVERNMENT OF INDIA
MINISTRY OF HOUSING AND URBAN AFFAIRS
LOK SABHA
UNSTARRED QUESTION NO. 3468
TO BE ANSWERED ON AUGUST 10, 2023
SMART CITIES PROJECTS
NO. 3468. SHRI MAHESH SAHOO:
Will the Minister of HOUSING AND URBAN AFFAIRS be pleased to state:
(a) the number of Smart Cities projects undertaken and completed so far;
(b) the present status of the projects in Odisha along with the details of projects which were sanctioned, tendered and stipulated to get completed; and
(c) the reasons for the non-completion of these projects, project-wise?
ANSWER
THE MINISTER OF STATE IN THE MINISTRY OF HOUSING AND URBAN AFFAIRS
SHRI KAUSHAL KISHORE
(a) to (c) : Government of India launched the Smart Cities Mission (SCM) on 25 June 2015. 100 Smart Cities have been selected through 4 rounds of competition from January 2016 to June 2018.
As on 7 July 2023, work orders have been issued by 100 Smart Cities in 7,978 projects of which 5,909 projects (74%) have been completed. ₹ 73,454 crore has been released for 100 Smart Cities of which ₹ 66,023 crore (90%) has been utilized.
As regards the State of Odisha, 2 cities i.e., Bhubaneswar & Rourkela have been selected for development as Smart Cities. Various projects being implemented by these cities, inter alia, include setting up of Integrated Control & Command Centres (ICCCs), Place-making, Smart Roads, Urban Knowledge Centre, Upgradation of Stadium, Market Area Re-development, etc. Details of physical and financial progress of Smart Cities in Odisha is given below: –
(Amount ₹ in crore)
Smart
City
|
Funds
Released
|
Utilization
|
Ongoing
|
Completed
|
Total
|
No.of
Projects
|
Amount
|
No.of
Projects
|
Amount
|
No.of
Projects
|
Amount
|
Bhubaneswar
|
998 #
|
885
|
9
|
607.71
|
26
|
1552.06
|
35
|
2159.77
|
Rourkela
|
890
|
782
|
5
|
357.62
|
59
|
1155.24
|
64
|
1512.86
|
Total
|
1,888
|
1,667
|
14
|
965.33
|
85
|
2,707.30
|
99
|
3,672.63
|
(Source: SCM Geospatial Management Information System (GMIS) as on 7 July 2023) (# Includes Funds released to Bhubaneswar under CITIIS Programme : ₹ 7.93 crore)
The period of implementation of SCM has been extended upto June 2024 and all Smart Cities, including those in Odisha, are expected to complete their projects within the stipulated time.