Pradhan Mantri Awas Yojana Constructed House during each of the last three years

Pradhan Mantri Awas Yojana Constructed House during each of the last three years

GOVERNMENT OF INDIA
MINISTRY OF HOUSING AND URBAN AFFAIRS 

LOK SABHA

STARRED QUESTION NO. 429
TO BE ANSWERED ON MARCH 25, 2021 

CONSTRUCTION OF HOUSES UNDER PMAY

Pradhan%2BMantri%2BAwas%2BYojana%2BConstructed%2BHouse
NO. 429. SHRI SADASHIV KISAN LOKHANDE

Will the Minister of HOUSING AND URBAN AFFAIRS be pleased to state:

(a) the total number of urban houses which were projected to be constructed in the country, particularly in Shirdi Parliamentary Constituency in Maharashtra under Pradhan Mantri Awas Yojna (PMAY) during each of the last three years, location-wise;

(b) the number of houses which have been contructed as on date and the number of those which are under construction/getting delayed along with their locations, particularly in the Shirdi Parliamentary Constituency; and

(c) the reasons behind the delay in the construction of such houses and the time by which these houses are expected to be completed?

ANSWER
THE MINISTER OF STATE (INDEPENDENT CHARGE) OF
THE MINISTRY OF HOUSING AND URBAN AFFAIRS

(SHRI HARDEEP SINGH PURI)

(a) to (c) A statement is laid on the Table of the House.

Statement referred to in reply to Lok Sabha Starred Question No. 429 to be answered on March 25, 2021 regarding CONSTRUCTION OF HOUSES UNDER PMAY

(a)&(b) Under Pradhan Mantri Awas Yojana-Urban (PMAY-U) Mission, during the last three years, viz.,2017-18, 2018-19 and 2019-20, about 78 lakh houses had been sanctioned in the country. The sanctioned houses include about

9.85 lakh for the State of Maharashtra including 5,039 houses in the Shirdi Parliamentary Constituency. The location wise details of houses sanctioned during the last three years i.e. 2017-20 and the details of houses sanctioned, completed, under construction in Shirdi Parliamentary Constituency under PMAY-U are annexed as Annexure.

(c) The houses sanctioned under PMAY-U are targeted to be completed by the year 2022.

 Annexure referred in reply to Lok Sabha Starred Q. No. *429 due for 25-03-2021

Year wise houses sanctioned during each of the last three years and progress of construction of houses since inception of Mission in the Country and in Maharashtra along with location wise details thereof for Shirdi Parliamentary Constituency under PMAY-U

Sr.

No.

Location

HousesSanctionedinlastth

reeyears
(Nos)


Progress of houses sanctioned since Inception

(Nos)

2017-18

2018-19

2019-20

Sanctioned

Completed

Under various stages of construction

1

AllIndia

20,70,616

33,09,898

24,19,662

1,10,86,682

43,54,855

32,23,425

2

Maharashtra

72,697

6,43,989

2,69,054

12,78,924

4,30,388

2,69,935

3

Shirdi
Parliamentary Constituency

Akole

323

4

343

53

68

4

Deolali Pravara

366

161

531

45

167

5

Kopargaon

27

253

368

858

371

158

6

Nevasa

593

3

602

67

134

7

Rahta Pimplas

351

12

400

75

30

8

Sangamner

8

274

58

573

249

38

9

Shirdi

1

445

16

473

33

175

10

Shrirampur

747

959

70

2,080

727

293

Total for

Shirdi

783

3,564

692

5,860

1,620

1,063

Source: Lok Sabha