(a) No, Sir. The National Heritage City Development and Augmentation Yojna (HRIDAY) is a central sector scheme and the funds are directly released to the cities.Out of the total sanctioned funds of Rs. 418.06 crore, an amount of Rs. 402.44 crore (96.26%) has been released.
(b) to (d) The details are attached as Annexure–A.
S.
No.
|
Name of the Project |
Sanction Date |
Amount released (in crore) |
Progress
Status (as on
31.03.2019)
|
UC
Received
till 31.03.2019
(in crore)
|
1
|
Landscape Improvements and Historic Edge Delineation of the Rambagh Garden |
07.12.2015 | 1.71 | 95% progress |
1.71
|
2
|
Restoration & Adaptive Reuse of Rambagh Gate | 07.12.2015 | 3.28 | Completed |
0.95
|
3
|
Comprehensive road development and up-gradation of 21 major roads leading to Golden Temple |
10.10.2016 | 31.27 | Completed | 29.31 |
4
|
Reorganizing Connectivity and Linkages through Streetscape and Landscape improvement at GolBagh |
10.10.2016 | 4.99 | Completed |
3.79
|
5
|
Comprehensive Improvement of a mobility corridor along the outer and inner circular road |
10.10.2016 | 4.88 | Completed |
3.89
|
6
|
Revitalization and Infrastructure Development at 40 Khoo, or 40 Wells and Colonial Period Power House |
10.10.2016 | 8.36 | 65% progress |
5.39
|
7
|
Development of an Environmental Park at the UBDC Canal | 10.10.2016 | 1.14 | 70% progress |
0.78
|
8
|
Structural retrofitting and up-gradation of the historic fabric of the colonial period building of the DC Office |
10.10.2016 | 1.95 | 85% progress |
1.58
|
9
|
Up-gradation of the Maharaja Ranjit Singh Panorama | 10.10.2016 | 0.49 | Completed |
0.40
|
10 | Interpretative Signage in the City with Sensors | 14.10.2016 | 2.13 | 50% progress |
0.68
|
11 | Heritage lighting for proper illumination of various sites | 5.09.2018 | 1.99 | 90% progress |
0.79
|
12 |
Conservation of the historic gates and improvement in the Heritage Zone4 – Circular Road – Historic Connector |
22.10.2018 | 11.23 | 45% progress |
4.75
|
Total
|
73.57 | 54.02 |
S.
No.
|
Name of the Project |
Sanction Date |
Amount released (in crore) |
Progress
Status (as on
31.03.2019)
|
UC
Received
till 31.03.2019
(in crore)
|
1
|
Up-gradation of Approach roads to Heritage Sites | 28.10.2015 | 10.01 | Completed | 12.15 |
2
|
Development of Heritage Walk | 28.10.2015 | 2.32 | Completed | |
3
|
Development of Amaravati Pond (NunegundamCheruvu) | 21.08.2018 | 4.27 | 60% progress |
1.82
|
Total
|
16.60 | 13.97 |
S.
No.
|
Name of the Project |
Sanction Date |
Amount released (in crore) |
Progress
Status (as on
31.03.2019)
|
UC
Received
till 31.03.2019
(in crore)
|
1
|
Development of Heritage Walk connecting Akbari Quila and Soniji ki Nasiya |
5.01.2016 | 4.41 | Completed |
2.93
|
2
|
Development of Jaipur Road Precinct | 4.07.2016 | 2.83 | Completed |
1.21
|
3
|
Development of Pushkar Heritage Walk | 4.07.2016 | 4.92 | Completed |
2.73
|
4
|
Development of Subhash Udyan | 4.07.2016 | 10.61 | Completed | 10.61 |
5
|
Annasagar Lakefront Up-gradation | 19.10.2016 | 9.35 | Completed |
7.80
|
6
|
Development of Vehicular Surface Parking at Longia Hospital, Ajmer |
1.02.2019 | 2.05 | Completed |
0.83
|
7
|
Development of Rail Museum at Ajmer | 14.01.2019 |
– *
|
25% progress |
–
|
Total
|
34.17 | 26.11 |
Badami (Karnataka)
S. No. |
Name of the Project |
Sanction Date |
Amount released (in crore) |
Progress
Status (as on
31.03.2019)
|
UC
Received till 31.03.2019
(in crore)
|
1
|
Development of Sullage Treatment Plant in Takkote Village. (Replaced by underground drainage work) |
23.06.2016 |
0.42
|
Completed |
0.37
|
2
|
Zero Waste Management for Badami Town | 29.06.2016 |
2.42
|
Completed |
1.84
|
3
|
Integrated Development and Improvement of Arterial Road, Transportation Infrastructure, Parking and Road Signage |
29.06.2016 | 16.19 |
70%
progress
|
11.18 |
Total
|
19.03 | 13.39 |
S.
No.
|
Name of the Project |
Sanction Date |
Amount released (in crore) |
Progress
Status (as on
31.03.2019)
|
UC
Received
till 31.03.2019
(in crore)
|
1
|
Vegetable market square | 4.07.2016 | 2.49 | Completed |
1.38
|
2
|
Sidheshwar Mahadev Precinct | 4.07.2016 | 2.54 | Completed |
1.41
|
3
|
Darshan Path – Teen Batti | 4.07.2016 | 1.41 | Completed |
1.10
|
4
|
Development of heritage zone 01 Dwarkadhish temple square | 14.10.2016 | 2.14 | Completed |
1.45
|
5
|
Development of heritage zone 04 Main Processional Street (Darshan Path) from Iskon Gate to Dwarkadhish temple |
14.10.2016 | 4.49 | Completed |
3.08
|
6
|
Development of Bet Dwaraka Darshan Circuit | 24.08.2017 | 10.69 |
40%
progress.
|
5.30
|
7
|
Revitalization of Vegetable Market, Brahma Kund, Hari Kund and Savitri Vav at Dwaraka |
24.12.2018 | 2.10 |
30%
progress
|
0.84
|
8
|
Installation of CCTV Cameras and Wi-Fi Systems in the identified Heritage Zones in Dwaraka |
27.02.2019 | 1.90 |
60%
progress
|
0.76
|
Total
|
27.76 | 15.32 |
S.
No.
|
Name of the Project |
Sanction Date |
Amount released (in crore) |
Progress
Status (as on
31.03.2019)
|
UC
Received
till 31.03.2019
(in crore)
|
1
|
Development of Ghats and Sarovars at Gaya: Brahmsat and Baitarani Sarovar |
31.03.2016 | 5.86 |
75%
progress
|
4.69
|
2
|
Development of Ghat and Vishnupad temple complex | 29.12.2016 | 7.94 |
45%
progress
|
7.02
|
3
|
Development of Akshay Vat Complex (Zone-2) at Gaya | 29.12.2016 | 1.61 |
88%
progress
|
1.29
|
4
|
Development of Connecting pathway- Dungeshwari hill to Mahabodhi temple (Zone-6) at Bodh Gaya |
29.12.2016 | 7.60 |
70%
progress
|
7.36
|
5
|
Development of Sita Kund Temple Complex | 12.09.2018 | 5.99 |
80%
progress
|
3.21
|
6
|
Development of Pita Maheshwar Sarovar | 12.09.2018 | 1.95 |
80%
progress
|
0.99
|
7
|
Beautification and Development of Ram Kund, Ram Sagar, Godavari and Singra Sthan Sarovar |
18.02.2019 | 4.71 |
15%
progress
|
–
|
Total
|
35.66 | 24.56 |
S.
No
|
Name of the Project |
Sanction Date |
Amount released (in crore) |
Progress
Status (as on
31.03.2019)
|
UC
Received
till 31.03.2019
(in crore)
|
1
|
Development and Infrastructure Up-gradation around Ekambareswarar Temple |
17.02.2016 |
9.89 |
Completed |
8.40
|
2
|
Development and Infrastructure Up-gradation around Varadharaja Perumal Temple Zone. |
17.02.2016 | 7.63 | Completed |
6.66
|
3.
|
Development and Infrastructure Works Around Kamatchi Amman Temple |
10.10.2017 |
1.96 |
90% progress |
1.76
|
Total
|
19.48 | 16.82 |
Mathura (Uttar Pradesh)
S.
No.
|
Name of the Project |
Sanction Date |
Amount released (in crore) |
Progress
Status (as on
31.03.2019)
|
UC
Received
till 31.03.2019
(in crore)
|
1
|
Redevelopment and Revitalization of Vrindavan Parikrama Marg |
08.03.2016 |
7.68
|
Completed |
4.23
|
2
|
Krishna Janmabhoomi Precinct | 29.12.2016 |
5.20
|
90%
progress
|
3.32
|
3
|
Revitalization of the Historic Chatta Bazaar | 29.12.2016 |
2.46
|
70%
progress
|
2.46
|
4
|
Rejuvenation of the Historic Vishram Ghat | 29.12.2016 |
1.45
|
70%
progress
|
1.45
|
5
|
Façade Lighting at Potra Kund | 14.01.2019 |
4.96
|
90%
progress
|
1.59
|
6
|
Installation of CCTV Cameras at Krishna Janmsthan, Vrindavan Parikrama Marg and Vishram Ghat |
14.01.2019 |
-*
|
50%
progress
|
–
|
7
|
Beautification of Krishnapuri Tiraha | 14.01.2019 |
-*
|
50%
progress
|
–
|
8
|
Installation of Street Furniture etc. | 14.01.2019 |
-*
|
10%
progress
|
–
|
Total
|
21.75 | 13.05 |
S.
No.
|
Name of the Project |
Sanction Date |
Amount released (in crore) |
Progress
status (as on
31.03.2019)
|
UC
Received
till 31.03.2019
(in crore)
|
1
|
Development of Landscape Garden by using treated water from waste water treatment plant at Banki Muhana |
31.03.2016 |
3.62
|
Completed |
3.62
|
2
|
Landscape development of Shri Jagannatha Ballabh Matha Garden |
10.10.2016 |
7.04
|
75% progress |
3.52
|
3
|
Landscape development etc. along the River Front Atharnala | 10.10.2016 |
1.54
|
65% progress |
1.54
|
4
|
Improvement and facades up-gradation of Bada Odiya Matha and Ganga Mata Matha |
10.10.2016 |
1.47
|
75% progress |
0.73
|
5
|
Revival of Pokharis, Ponds located in 7 Jagaghara | 10.10.2016 |
0.79
|
Completed |
0.79
|
6
|
Retrofitting of building facades along the Parikrama Marg (periphery) of Shri Jagannatha Temple |
10.10.2016 |
1.66
|
67% progress |
1.19
|
Total
|
16.12 | 11.39 |
Velankanni (Tamil Nadu)
S.
No.
|
Name of the Project |
Sanction Date |
Amount released (in crore) |
Progress
Status (as on
31.03.2019)
|
UC
Received
till 31.03.2019
(in crore)
|
1
|
Development of support infrastructure at Velankkanni | 21.12.2015 |
0.77
|
Completed |
0.17
|
2
|
Heritage linked infrastructure development of Three Delineated zones |
29.12.2016 |
9.60
|
Completed |
8.68
|
3.
|
Additional Heritage linked infrastructure development of Three Delineated zones |
16.11.2017 |
8.66
|
85%
progress
|
5.52
|
Total
|
19.03 | 14.37 |
Varanasi (Uttar Pradesh)
S.
No.
|
Name of the Project |
Sanction Date |
Amount released (in crore) |
Progress
Status (as on
31.03.2019)
|
UC
Received
till 31.03.2019
(in crore)
|
1
|
Construction of 10 approach Roads to various heritage sites | 01.06.2015 |
7.91
|
Completed |
7.48
|
#
|
Development of Dashashwamedh – Godowlia Culture Quarter. | 18.04.2016 |
0.19
|
Dropped |
0.15
|
2
|
Redevelopment of Town Hall as Heritage Centre | 18.04.2016 |
2.26
|
Completed |
2.25
|
3
|
Development of 24 Roads leading to various heritage sites | 13.04.2016 | 21.69 | Completed | 21.00 |
4
|
Development of Heritage precinct of Road Connecting Durgakund, Kurushetra Pokhra and AssiGhat |
29.06.2016 |
1.42
|
Completed |
1.08
|
5
|
Carrying out Heritage Artistic Paint Work | 23.08.2016 |
0.07
|
Completed |
0.03
|
6
|
Heritage Walk around Kabir Chaura and Piplani Katra | 14.10.2016 |
2.30
|
Completed |
2.30
|
7
|
Development of 86 heritage sites | 14.10.2016 | 11.97 | Completed |
9.40
|
8
|
Implementation of Heritage Sensitive Infrastructure for LED Street Lighting at Old Kashi Zone |
15.05.2017 | 21.20 | Completed | 10.60 |
9
|
Thematic Development of 10 Roads leading to Various Heritage Sites |
30.05.2017 |
5.47
|
80%
progress
|
2.40
|
10. | Façade Lighting for Historic monument of Town Hall and Durga Mandir |
06.02.2018 |
1.03
|
Completed |
0.82
|
11. | Installation of Heritage Sensitive LED Street Lighting | 01.11.2018 | 12.78 | Completed |
7.44
|
Total
|
88.29 | 64.95 |
Warangal (Telangana)
S.
No.
|
Name of the Project |
Sanction Date |
Amount released (in crore) |
Progress
Status (as on
31.03.2019)
|
UC
Received
till 31.03.2019
(in crore)
|
1
|
Bhadrakali Lake Foreshore Development | 14.10.2015 | 20.27 |
80%
progress
|
11.11 |
2
|
Development work at 1000 pillar temple area | 28.03.2016 |
0.18
|
Completed |
0.18
|
3
|
Development work at Kazipeth Dargah | 28.03.2016 |
1.78
|
Completed |
1.73
|
4
|
Rejuvenation of pond at Padmakshi Temple and Development of Jain Sites of Hanamkonda Hill |
28.03.2016 |
1.62
|
Completed |
1.62
|
5
|
Revival and Development of Fort Warangal | 14.10.2016 |
8.97
|
50%
progress
|
6.11
|
Total
|
32.82 | 20.75 |
- (a) whether it is a fact that only 52 per cent of the amount has been released to the State Governments by the Union Government for different projects under Heritage City Development and Augmentation Yojana(HRIDAY);
- (b) if so, the details thereof and the projects undertaken by the State Governments during each of the last three years, State-wise;
- (c) the status of the projects undertaken by the States till 31st March, 2019; and
- (d) the total amount utilized for each project during the said period, project-wise and State-wise?
*****